project management

In an organization, project managers report directly to the head of a project management office (PMO). In this case, which statement is probably not true? The project management office will actually be responsible for direct management of A) the projects. Projects will be run by the functional organization and project managers expedite B) change control. The head of the project management office can strengthen the matrix as a project managers. C) manager of it will be easier for the PMO to ensure that the organizational process assets provided D are used.

Explanation / Answer

B. Projects will be run by the functional organization and project managers are expediting change control.

Project Management office is responsible for ensuring that the standards of the Project Management is maintained within the Organization. It is not a functional organization, rather a source of document that guides the Project managers in the practice and execution of the Project. Hence it is not a separate Functional organization but part of the entire Organization within which Project managers undertake the Projects and the PMO offers the supporting role along with controlling and the directive ones.