1. A business intelligence system supports _______. A. strategic planning and ex
ID: 3902536 • Letter: 1
Question
1. A business intelligence system supports _______.
A. strategic planning and executive decision making
B. just in time inventory decisions
C. customer service requirements
D. business process activities
2. Setting up a change control log to keep track of new system requirements is part of
what PMBOK area?
A. Cost Management
B. Quality Management
C. Time Management
D. Scope Management
3.Given the above figure, what is the late start time for task number 5?
A. 6 days
B. 7 days
C. 8 days
D. 9 days
Explanation / Answer
1. A
A business intelligence system supports strategic planning and executive decision making.
Business Intelligence System means for the integration and presentation of business information we are using lot of applications and methods and it supports strategic planning and executive decision making.
2. D
Setting up a change control log to keep track of new system requirements is part of Scope Management.
because Scope Management has the ebility to log and track of new system requirements but the quality and time and cost represents for maintaining the different trackings.
3.D
late start time for task number 5 is 9 days.
as in the above figure
plan move - 2 days
hire staff- 3 days
move records - 1 day.
so total is 6 days but in the given question it is late start time for task number 5 hence it will take 9 days.
Thanks have a great day.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.