Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Earned value measures: ROI, NPV and PBP Quality Progress against budget Status o

ID: 3908678 • Letter: E

Question

Earned value measures:

ROI, NPV and PBP

Quality

Progress against budget

Status of deliverables

If a project has an SPI of 90% and a CPI of 110%, it is:

over budget, behind schedule

under budget, behind schedule

over budget, ahead of schedule

under budget, ahead of schedule

Three types of estimates are:

Budgetary, fiscal and MIPPS

ROM, budgetary and definitive

ROI, NPV and PBP

PMI, ASPCA and OMDB

Three estimating methodologies are:

Budgetary, experiential and governmental

analogous or top down, detailed or bottom up and parametric

experiential, regression and experimental

by luck, by guess and by golly

Three types of dependencies are:

absolute, negative and positive

start-start, start-stop and pause-stop

mandatory, external and discretionary

relative, in-law and natural

A task has a most likely duration of 2 days, an optimistic duration of 1 day and a pessimistic duration of 3 days. What is the PERT method estimate of the duration of the task?

1 day

2 days

2.5 days

1.5 days

Earned value measures:

Scope

Time

Cost

All of the above

13) Project 1 has five bidders. Its value is $300,000, but will cost $40,000 to bid. What is its EMV?

$28,000

$260,000

$32,000

insufficient data

14) Project 2 has 100 bidders. Its value is $20,000,000, but will cost $200,000 to bid. What is its EMV?

$2,000

$20,000

$19,800,000

insufficient data

   15) If he can only bid on one project, a risk-seeking manager will bid on which one?

a) project 1

b) project 2

c) insufficient data

16) A face to face meeting is the best way to:

a) assess commitment

b) build consensus

c) mediate a conflict

d) give complex instructions

e) all the above

    17) Insurance is an example of:

risk avoidance

risk acceptance

risk transference

risk mitigation

    18) An important tool for use in communications planning is ______ _____.

    19) Meetings should have:

a)   purpose and outcomes

agendas

time boxes

logistical arrangements

all the above

According to the lecture, most important to the success of the project is:

user involvement

proper planning

clear vision and objectives

competent staff

      21) Managers frequently add a ______ ________ to budgets for unforeseen events.

Explanation / Answer

Please Note: As per Chegg Answering Guidelines, I should answer the first question only. I have answered 4 questions here. Please Post Separate for other Questions.

Q)

Earned value measures:

ROI, NPV and PBP

Quality

Progress against budget

Status of deliverables

Answer)

Earned value measures:

Progress against budget

EVM measure the progress achieved by the project against the budget.

Q)

If a project has an SPI of 90% and a CPI of 110%, it is:

over budget, behind schedule

under budget, behind schedule

over budget, ahead of schedule

under budget, ahead of schedule

Answer)

SPI of 90%, so project is behind schedule

CPI of 110%, means the project is under budget.

Thus the correct option will be:

under budget, behind schedule

Q) Three types of estimates are:

Budgetary, fiscal and MIPPS

ROM, budgetary and definitive

ROI, NPV and PBP

PMI, ASPCA and OMDB

Answer)

ROM, budgetary and definitive

The above are the 3 types of estimates.

Q)

A task has a most likely duration of 2 days, an optimistic duration of 1 day and a pessimistic duration of 3 days. What is the PERT method estimate of the duration of the task?

1 day

2 days

2.5 days

1.5 days

Answer)

E = (TOPT + 4 x TLIEKLY + TPESS) / 6

Estimation of the duration of the task =

(1+ 4x2 + 3) / 6 = 12/6 = 2

Thus the correct PERT method estimate of the duration of the task = 2 days.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote