Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

1. Earned value measures: a.ROI, NPV and PBP b.Quality c.Progress against budget

ID: 3908679 • Letter: 1

Question

1. Earned value measures:

a.ROI, NPV and PBP

b.Quality

c.Progress against budget

dStatus of deliverables

2. If a project has an SPI of 90% and a CPI of 110%, it is:

a.over budget, behind schedule

b.under budget, behind schedule

c.over budget, ahead of schedule

d.under budget, ahead of schedule

3.Three types of estimates are:

a.Budgetary, fiscal and MIPPS

b.ROM, budgetary and definitive

c.ROI, NPV and PBP

d.PMI, ASPCA and OMDB

4.Three estimating methodologies are:

a.Budgetary, experiential and governmental

b.analogous or top down, detailed or bottom up and parametric

c.experiential, regression and experimental

d.by luck, by guess and by golly

5.Three types of dependencies are:

a.absolute, negative and positive

b.start-start, start-stop and pause-stop

c.mandatory, external and discretionary

d.relative, in-law and natural

Explanation / Answer

Please Note: As per Chegg Answering Guidelines, I should answer the first question only. I have answered 4 questions here. Please Post Separate for other Questions.

Q)

Earned value measures:

ROI, NPV and PBP

Quality

Progress against budget

Status of deliverables

Answer)

Earned value measures:

Progress against budget

EVM measure the progress achieved by the project against the budget.

Q)

If a project has an SPI of 90% and a CPI of 110%, it is:

over budget, behind schedule

under budget, behind schedule

over budget, ahead of schedule

under budget, ahead of schedule

Answer)

SPI of 90%, so project is behind schedule

CPI of 110%, means the project is under budget.

Thus the correct option will be:

under budget, behind schedule

Q) Three types of estimates are:

Budgetary, fiscal and MIPPS

ROM, budgetary and definitive

ROI, NPV and PBP

PMI, ASPCA and OMDB

Answer)

ROM, budgetary and definitive

The above are the 3 types of estimates.