Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

6 (PC Repair Shop) From the calculations above, hiring one more worker design ca

ID: 390925 • Letter: 6

Question

6 (PC Repair Shop) From the calculations above, hiring one more worker design capacity, A) will always increase B) will always decrease C) might not increase 7 (PC Repair Shop) From the calculations above, hiring one more worker_utilization. A) will always increase B) C) might not decrease will always decrease (Serial Process) The diagram below shows a four-step serial process. The rate shown in each box is the process capacity of that operation. Operation 1 12/hr Operation 2 15/hr Operation 3 11/hr Operation 4 14/hr 8 (Serial Process) The bottleneck is A) Operation B) Operation 2 C) Operation 3D) Operation 4 9| (Serial Process) The process capacity of the entire system is A) 12/hr B) 15/hr C) 11/hr D) 14/hr E) 52/hr 10 (Serial Process) If the process capacity of the current bottleneck is increased by 2/hr, the new bottleneck will be A) Operation 1B) Operation 2 C) Operation 3D) Operation 4 11 When throughput (or flow rate) is measured, an insufficient supply of raw materials can be a bottleneck. A) Yes 0

Explanation / Answer

8) C) Operation 3. Correct option

Bottleneck operation is with highest process time.

9) C) 11/hr. Correct option

Process capacity is constrained by bottleneck.

10) A) Operation1. Correct option

Operation 1 produces 12 units per hour and operation 3 is now producing 13 units per hour.

11) A) Yes

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote