Question 1 A _____ is a precise point on the project schedule that indicates a s

ID: 3915228 • Letter: Q

Question

Question 1

A _____ is a precise point on the project schedule that indicates a specific completion point.

milestone

user acceptance point

beta system

deliverable

2.38095 points

Question 2

The old computer adage, which indicates the importance of input integrity controls, is _____.

garbage-to-garbage

garbage in, garbage out

bugs generate buys

information overload

2.38095 points

Question 3

For structured designs and programs, an analyst can determine input, process, output (IPO) ordering by examining the _____.

system flowchart only

structure chart only

system flowchart and structure charts

system sequence diagram (SSD)

2.38095 points

Question 4

The _____ is the point at which the increased cash flow exactly pays off the costs of development and operation.

milestone

float

breakeven point

2.38095 points

Question 5

A(n) ______ is a collection of interrelated components that collect, process, store, and provide as output the information needed to complete business tasks.

system

information system

subsystem

2.38095 points

Question 6

The objective of _____ is to calculate a percentage return so that the costs and benefits are exactly equal over the specified time period.

return on investment (ROI)

project evaluation and review technique (PERT)

cost/benefit analysis

2.38095 points

Question 7

An event that occurs outside the system, usually initiated by an external agent or actor, is called a(n) _____ event.

logical

external

temporal

2.38095 points

Question 8

Two of the most common graphical charting techniques are _____.

vertical charts and horizontal charts

line charts and series charts

bar charts and pie charts

printed charted and screen charts

2.38095 points

Question 9

Detailed algorithm logic can be described during design before it is actually coded using _____.

pseudocode

a structure chart

a decision tree

2.38095 points

Question 10

A relational database table is in _____ normal form if it has no repeating fields or groups of fields.

first

second

third

fourth

2.38095 points

Question 11

_____ sessions have been largely successful in reducing project development efforts and shortening the schedule.

Business process reengineering (BPR)

Group support system (GSS)

Swimlane

Joint application design (JAD)

2.38095 points

Question 12

A(n) _____ program is one that has one beginning and one ending.

iterative

structured

incremental

2.38095 points

Question 13

A _____ is provided by an outside company as a complete solution, including hardware and software.

turnkey system

custom-built system

packaged software

2.38095 points

Question 14

A(n) _____ provides authentication by using the person himself as the gateway into a secure system.

x-ray scanner

encryption key

biometric device

2.38095 points

Question 15

What does XML stand for?

Extended Module Links

External Machine Linkage

External Multiple Logging

Extensible Markup Language

2.38095 points

Question 16

Skills in a nontechnical area such as interviewing and team management are called _____.

inherent skills

technical skills

hard skills

soft skills

2.38095 points

Question 17

A _____ describes the purpose of the new system, the potential start and completion dates, and the key stakeholders and sponsors of the new system.

cost/benefit analysis

project schedule

work breakdown structure (WBS)

project charter

2.38095 points

Question 18

A report that is used primarily for strategic decision making is called a(n) _____ report.

executive

key

exception

summary

2.38095 points

Question 19

Skills in technical areas such as programming and network design are called _____.

business skills

soft skills

hard skills

2.38095 points

Question 20

A(n) _____ approach to the SDLC is used when the exact requirements of a system or needs of users are not well understood.

predictive

persistent

incremental

adaptive

2.38095 points

Question 21

The _____ approach is an SDLC approach that assumes the various phases of a project can be completed entire sequentially.

waterfall

artifact

prototype

2.38095 points

Question 22

A concept that allows subclasses to share the characteristics of their superclasses is called _____.

aggregation

encapsulation

multiplicity

inheritance

2.38095 points

Question 23

The purpose of the use case diagram is to identify the _____.

users of the system

system boundary

messages in the system

uses of the system

2.38095 points

Question 24

A(n) _____ is a representation of an important aspect of the real world.

methodology

tool

technique

model

2.38095 points

Question 25

Which of the following is the section of the three-layer architecture that interacts with the database?

Business logic layer

View layer

Data layer

2.38095 points

Question 26

The term “_____” refers to all the people who have an interest in the successful implementation of the system.

users

clients

middle managers

stakeholders

2.38095 points

Question 27

A technique that seeks to alter the nature of the work done in a business function, with the objective of radically improving performance, is called _____.

business process reengineering

strategic planning

information systems strategic planning

2.38095 points

Question 28

_____ feasibility asks the question: “Is the anticipated value of the benefits greater than projected costs of development?”

Technological

Economic

Cultural

2.38095 points

Question 29

Which of the following is that part of the three-layer architecture that contains the programs that implement the business rules of the application?

Data layer

View layer

Business logic layer

User layer

2.38095 points

Question 30

A(n) _____ in system development is a collection of guidelines that help an analyst complete a system development activity or task.

iteration

model

technique

2.38095 points

Question 31

The primary objective to keep in mind during the design of input mechanisms is that _____.

costs are controlled

the system is user friendly

the system functions correctly

input data must be error free

2.38095 points

Question 32

_____ are programs that send requests to servers using one or more of the standard Web resource request protocols.

Virtual private networks (VPNs)

Activity data matrices

Clients

2.38095 points

Question 33

_____ should clearly state deadlines for questions, proposed delivery, and other important events.

Enterprise resource planning (ERP)

Business process reengineering (BPR)

A request for proposal (RFP)

2.38095 points

Question 34

A security control that determines who has access to a system and its data is a(n) _____ control.

user security

access

administration

2.38095 points

Question 35

The _____ states that events should be included during analysis only if the system would be required to respond under perfect conditions.

perfect technology assumption

risk control assumption

2.38095 points

Question 36

_____ refers to a loosely coupled group of people and resources that work together as though they were an organization.

Virtual organization

World Wide Web

Private network

2.38095 points

Question 37

The _____ is a sequence of tasks that cannot be delayed without causing the project to be completed late.

float

critical path

payback period

2.38095 points

Question 38

A(n) _____ is a field or set of fields used to uniquely identify each row.

primary key

foreign key

object identifier

attribute

2.38095 points

Question 39

A(n) _____ is a good tool for monitoring the progress of a project as it moves along.

entity-relationship diagram (ERD)

Gantt chart

work breakdown structure (WBS)

context diagram

2.38095 points

Question 40

A business intelligence system supports _____

strategic planning and executive decision-making

just-in-time inventory decisions

customer service requirements

2.38095 points

Question 41

In structured design, an executable entity comprised of a set of modules is called a(n) _____.

server

task

system

computer program

2.38095 points

Question 42

A technique used to document dialog designs by showing a sequence of display screen sketches is _____.

storyboarding

an event list

an interface diagram

2.38095 points

Save and Submit

Click Save and Submit to save and submit. Click Save All Answers to save all answers.

A.

milestone

B.

user acceptance point

C.

beta system

D.

deliverable

Explanation / Answer

Question 1:-
A. MileStone
Mislestone marks the specific completion point in the on going project.

Question 2:-
B. garbage in, garbage out
It improves or highlights the data quality .

Question 3:-
B. structure chart only

Question 4:-
C. breakeven point
The actual answer is payback period but there is no option in the list . So the next relevant option is breakeven point which means it is also the point where the return on investment will be made.

Question 5:-
B.information system

Question 6:-
A. return on investment (ROI)

Question 7:-
B. external

Question 8:-
C.bar charts and pie charts

Question 9:-
A. pseudocode

Question 10:-
A. first
First Normal form rule is that it should be atomic which means doesn't have to be group of fileds.

As per the chegg policy I am not able to answer mroe than these questions . kindly understand and post the remaining as new question