Which of these statements regarding time-cost tradeoffs in CPM networks is true?
ID: 391983 • Letter: W
Question
Which of these statements regarding time-cost tradeoffs in CPM networks is true? OA. Crashing is not possible unless there are multiple critical paths. O B. The crash time always exceeds the normal time O C. Crashing a project often reduces the length of long-duration, but noncritical, activities. D. Crashing shortens the project duration by assigning more resources to one or more of the critical tasks. E. Activities not on the critical path can never be on the critical path, even after crashingExplanation / Answer
D. Crashing shortens the project duration by assigning more resources to one or more of the critical tasks
Crashing is the activity that reduces the project schedule by prioritizing the critical tasks by assigning additional resources.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.