Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The product design group of lyengar Electric Supplies, Inc., has determined that

ID: 392312 • Letter: T

Question

The product design group of lyengar Electric Supplies, Inc., has determined that it needs to design a new series of switches. It must decide on one of three design strategies. The market forecast is for 400,000 units. The better and more sophisticated the design strategy and the more time spent on value engineering, the less will be the variable cost. The chief of engineering design, Dr. W. L. Berry, has decided that the following costs are a good estimate of the initial and variable costs connected with each of the three strategies explained below Low-tech: a low-technology, low-cost process consisting of hiring several new junior engineers. This option has a fixed cost of $40,000 and variable-cost probabilities of 0.3 for $0.52, 0.4 for $0.46, and 0.3 for $0.45 Subcontract: a medium-cost approach using a good outside design staff. This approach would have a fixed cost of $60,000 and variable-cost probabilities of 0.6 of $0.48, 0.2 of $0.45, and 0.2 of $0.43 High-tech: a high-technology approach using th $75,000 and variable-cost probabilities of 0.8 of $0.44 and 0.2 of $0.34 e very best of the inside staff and the latest computer-aided design technology. This approach has a fixed cost of What is the best decision based on an expected monetary value (EMV) criterion? (Note: We want the lowest EMV, as we are dealing with costs in this problem.) O Low-tech O Subcontract O High-tech

Explanation / Answer

Answer:

Explanation:

EMV:

Low Tech:

Subcontract:

High tech: