Please Solve letter E The Action Toy Company has decided to manufacture a new tr
ID: 392751 • Letter: P
Question
Please Solve letter E
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek Performance Time (seconds) 24 28 Task Predecessors 10 28 B, C D, E This exercise only contains parts b, c, d, e, and f b) Given the demand, the cycle time for the production of the new train set-32 seconds (round your response to one decimal place). c) The theoretical minimum number of workstations 4 (round your response up to the next whole number) d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) Task Workstation # Station 1 Station 2 Station 3 Station 3 Station 4 Station 5 Were you able to assign all the tasks to the theoretical minimum number of workstations? No e) The total idle time per cycle for the processseconds (enter your response as a whole number)Explanation / Answer
Idle time per cycle for the process = Cycle time - Performance time
Task A = 32 - 24 = 8
Task B = 32 - 28 = 4
Task C = 32 - 14 = 18
Task D = 32 - 14 = 18
Task E = 32 - 10 = 22
Task D = 32 - 28 = 4
Do give a positive rating if you think this answer helped
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.