Problems 357 The GHI Company produces models A, B, C, and D on an assembly line
ID: 393403 • Letter: P
Question
Problems 357 The GHI Company produces models A, B, C, and D on an assembly line that operates 250 eight- hour days per year. The demand forecasts are: 8. Model Annual forecast 1,000 3,000 7,000 9,000 a. Determine the mixed-model master production schedule for a daily batch and hourly batch with minimum batch sizes. b. Determine the schedule of production for an eight-hour day using mixed-model minimum batch production. The GHI Company makes air conditioners, in either the standard model or additionally with a special option it calls the "turbo-charger using the following indented bill of materials. The air conditioners are assembled at a rate 600 per five-day week, and the turbo-charger is added to every fourth unit. Develop the 10-week MRP record for the turbo-charger, using a one-week lead time, no safety stock, a lot size of 800, and a starting inventory of 200. Air Conditioner 9. Part no. 101 (1 required) Part no. 102 (1 required) Part no. 103 (1 required) Turbo-charger assembly & required) Coupling (1 required)Explanation / Answer
Mixed Model Production sequence
It refers to distribute the production of different product types evenly over the course of a day
Here 250 days are available in a year
Steps for determining the MMP schedule
Daily requirements
A= 1000/250= 4
B= 3000/250=12
C= 7000/250 = 28
D = 9000/250= 36
Total products= 36+28+12+4= 80
Repeating sequence
Determine the largest integer that divides evenly into all daily requirements of all the products
Here the largest integer divisor =4
The ratio = 1:3:7:9
Sum of ratios = 20
Each repeating sequence will have 20 units and 1 unit of A , 3 units of B, 7 units of C, 9 units of D
Hourly sequence
Hourly requirement
A= 4/8=0.5
B=12/8 = 1.5
C= 28/8= 3.5
D= 36/8= 4.5
Changing them to integer the ratio would be
1:2:4:5
Total products per hour= 1+2+4+5=12
1 unit of A 2 units of B, 4 units of C and 5 units of D
b) Production plan according to the daily MMP sequence(ratio1:3;7:9)
A possible sequence would be
ABBBCCCCCCCDDDDDDDDD
This is the somewhat batch type and if we change it to mixed model type
ABCDBCDBCDCDCDCDCDDD this is the best possible mixed model production sequence
Please comment of any doubt
rateme
thanks