Use the following data for questions 7 & 8 Bill of Material Lot Size Rule Lead T
ID: 395499 • Letter: U
Question
Use the following data for questions 7 & 8
Bill of Material
Lot Size Rule
Lead Time
Door
2
FOQ = 10
2 weeks
hinges
4
FOQ = 40
4 weeks
screws (h)
24
FOQ = 50
1 week
knobs
2
FOQ = 10
3 weeks
screws (k)
4
FOQ = 25
1 week
Stain
1
FOQ = 25
1 week
Week
1
2
3
4
5
6
7
8
9
Door Gross Requirements
6
10
Beginning Inventory
Door
hinges
screw (h)
knobs
screw (K)
Stain
2
20
30
5
15
10
For the data provided determine the Inventory Record using a FOQ lot size rule for the hinge.
For the data provided determine the Inventory Record using a FOQ lot size rule for the screw (H).
Bill of Material
Lot Size Rule
Lead Time
Door
2
FOQ = 10
2 weeks
hinges
4
FOQ = 40
4 weeks
screws (h)
24
FOQ = 50
1 week
knobs
2
FOQ = 10
3 weeks
screws (k)
4
FOQ = 25
1 week
Stain
1
FOQ = 25
1 week
Week
1
2
3
4
5
6
7
8
9
Door Gross Requirements
6
10
Beginning Inventory
Door
hinges
screw (h)
knobs
screw (K)
Stain
2
20
30
5
15
10
Explanation / Answer
It is assumed that the doors, hinges and screws are needed in the week of requirement only.
Door /Week 1 2 3 4 5 6 7 8 9 Requirement 0 0 0 0 0 6 0 0 10 Inv. On Hand 2 2 2 2 2 2 6 6 6 Scheduled receipts 0 0 0 0 0 0 0 0 0 Net requirements 0 0 0 0 0 4 0 0 4 PlannedReceipts 0 0 0 0 0 10 0 0 10 Planned Orders 0 0 0 10 0 0 10 0 0Related Questions