Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate and times appea r in the accompanying table Activity Immediate Predecessor(s Time (days) 10 A, D E, F This exercise contains only parts b, c, and d b) The criical activities for the leadership training program development project are B-D E G c) The project length for the leadership training program development project28 days d) Slack time for each of the activities is: Activity Slack Time 13

Explanation / Answer

Solution:

Activity

Time

ES

EF

LS

LF

Slack(LS- ES) or(LF-EF)

A

4

0

4

13

17

13

B

7

0

7

0

7

0

C

3

0

3

11

14

11

D

10

7

17

7

17

0

E

3

17

20

17

20

0

F

6

3

9

14

20

11

G

8

20

28

20

28

0

So from the slack we can find that Critical path activities are BDEG and Project length is (7+10+3+8) = 28days

Activity

Time

ES

EF

LS

LF

Slack(LS- ES) or(LF-EF)

A

4

0

4

13

17

13

B

7

0

7

0

7

0

C

3

0

3

11

14

11

D

10

7

17

7

17

0

E

3

17

20

17

20

0

F

6

3

9

14

20

11

G

8

20

28

20

28

0