Question 1 1. Earned value measurement is a technique: Answer Suitable for risk
ID: 403170 • Letter: Q
Question
Question 1
1.
Earned value measurement is a technique:
Answer
Suitable for risk monitoring and control
Unsuitable for risk monitoring and control
Suitable for risk monitoring but unsuitable for control
Unsuitable for risk monitoring but suitable for control
Question 2
1.
Monte Carlo simulation is a technique used as part of:
Answer
Risk identification
Risk assessment
Risk monitoring and control
Risk handling
Question 3
1.
Nominal work groups and the Delphi Techniques are used as part of which risk management process?
Answer
Risk identification
Risk assessment
Risk monitoring and control
Risk handling
Question 4
1.
An objective source for risk identification is:
Answer
Lessons learned files
Program documentation evaluations
Current performance data
All of the above
Question 5
1.
If there%u2019s a 40% chance of making $1 million and a 60% chance of losing $600,000, then the expected monetary outcome is.
Answer
<$400,000>
<$40,000>
$360,000
<$360,000>
Question 6
1.
Proper risk management is:
Answer
Reactive rather than proactive
Proactive rather than reactive
Achievable only by reliance on Monte Carlo simulation
Evidenced by the use of the Delphi Technique
Question 7
1.
In which life cycle phase is the total project risk generally the least?
Answer
Initiation / Approval
Planning
Execution
Closure
Question 8
1.
The process that identifies, evaluates, selects and implements one or more strategies to set risk at an acceptable level is:
Answer
Risk planning
Risk assessment
Risk handling
Risk monitoring and control
Question 9
1.
Risk mitigation or control:
Answer
Does not eliminate a risk but seeks to reduce it without altering the requirements.
Eliminates a risk by reducing it without altering the requirements.
Eliminates a risk by changing the requirements
Eliminates a risk by reducing the requirements
Question 10
1.
A technique that uses a series of probability distributions and then transforms them into various risks is called:
Answer
Probability estimating
Monte Carlo simulation
Estimating simulation
Black box analysis
Explanation / Answer
1. Earned value measurement is a technique: Answer Suitable for risk monitoring and control ======================================================================================================================================================================================== Question 2 1. Monte Carlo simulation is a technique used as part of: Answer Risk assessment ======================================================================================================================================================================================== Question 3 1. Nominal work groups and the Delphi Techniques are used as part of which risk management process? Answer Risk identification ======================================================================================================================================================================================== Question 4 1. An objective source for risk identification is: All of the above ======================================================================================================================================================================================== Question 5 1. If there%u2019s a 40% chance of making $1 million and a 60% chance of losing $600,000, then the expected monetary outcome is. Answer ======================================================================================================================================================================================== Question 6 1. Proper risk management is: Answer Proactive rather than reactive ======================================================================================================================================================================================== Question 7 1. In which life cycle phase is the total project risk generally the least? Answer closure ======================================================================================================================================================================================== Question 8 1. The process that identifies, evaluates, selects and implements one or more strategies to set risk at an acceptable level is: Answer Risk handling ======================================================================================================================================================================================== Question 9 1. Risk mitigation or control: Answer Eliminates a risk by reducing it without altering the requirements. ======================================================================================================================================================================================== Question 10 1. A technique that uses a series of probability distributions and then transforms them into various risks is called: Answer Monte Carlo simulationRelated Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.