Suppose the length of critical path in a project is 50 days. The probability of
ID: 403427 • Letter: S
Question
Suppose the length of critical path in a project is 50 days. The probability of completing the project within 50 days is: Answer Less than 50% Greater than 50% Equal to 50% Can not be determined from the above data Suppose the length of critical path in a project is 50 days. The probability of completing the project within 50 days is: Suppose the length of critical path in a project is 50 days. The probability of completing the project within 50 days is: Less than 50% Greater than 50% Equal to 50% Can not be determined from the above data Less than 50% Greater than 50% Equal to 50% Can not be determined from the above dataExplanation / Answer
Answer. ) less than 50%
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.