***NOT INTERESTED IN PRIVATE TUTORS*** Only willing to work with Chegg members and deem points credit to those who can help through Chegg only.***(Please show work - No longer rating or offering points unless work can be proven and correct.) Tired of paying for additional chegg points and receiving wrong answers and folks are just guessing so that can get rated and rewarded points.** Activity First Week Second Week Third Week 1-2 $12 $16 $ --- 2-5 6 8 10 5-7 7 8 11 7-11 7 11 --- 11-13 4 8 10 1-3 12 14 19 3-8 5 --- --- 8-11 12 13 14 3-9 14 16 16 9-12 8 8 10 12-13 7 11 --- 1-4 10 14 18 4-6 12 14 18 6-10 11 12 --- 10-12 14 15 --- weeks.
Determine the costs to shorten the project.
1st Week Cost = Hint: Between 10 and 14
2nd Week Cost =
3rd Week Cost =
4th Week Cost = Hint: Between 16 and 21
Note: For each week you are to include only the cost of shortening the activities in that particular week. Activity First Week Second Week Third Week 1-2 $12 $16 $ --- 2-5 6 8 10 5-7 7 8 11 7-11 7 11 --- 11-13 4 8 10 1-3 12 14 19 3-8 5 --- --- 8-11 12 13 14 3-9 14 16 16 9-12 8 8 10 12-13 7 11 --- 1-4 10 14 18 4-6 12 14 18 6-10 11 12 --- 10-12 14 15 --- The Department of Transportation has found that a proposed highway project is not going to be completed before the end of the summer. They have asked the contractor to prepare cost figures to shorten the project by up to 4 weeks. The following table shows the Crashing Costs for each activity. For example, if you needed to shorten Activity 1-2 by 1 week this would cost If you needed to shorten the same activity by 2 weeks it would cost $16. Note: If an activity lists a cost of $---, then this activity cannot be any shorter. Currently, the Length of the Project is Determine the costs to shorten the project. 1st Week Cost = 2nd Week Cost = 3rd Week Cost = 4th Week Cost =
Explanation / Answer
REASON:
CRASHING ACTIVITIES: 11-13 AND 12-13
COST = 4+7 =11
REASON:
CRASHING ACTIVITIES: 11-13 AND 12-13
COST = 8+11 =19
REASON:
CRASHING ACTIVITIES: 1-4 AND 2-5
COST = 18+10 =28