I will surely rate... A branch of Punjab National Bank has only one typist. Sinc
ID: 404083 • Letter: I
Question
I will surely rate...
A branch of Punjab National Bank has only one typist. Since the type work varies in length (number of pages to be typed), the typing rate is random!; distributed approximating a Poisson distribution with mean service rate ui letters per hour. The letters arrive at a rate of 5 per hour during the entire 8-hom work day. If the typewriter is valued at Rs. 1.50 per hour, determine Equipment utilization. The per cent time that an arriving letter has to wait. Average system time. Average cost due to waiting on the part of typewriter.Explanation / Answer
lambda = 5 per hr
meu = 8 per hr
1.(Eqilibrium utilization) roh = lambda/muu = 5/8 = 0.625
2.the percent time arriving letter has to wait = % time the typewriter remains busy
= 62.5%
3.Avg system time Ws
= 1/(meu-lambda)
= 1/(8-5)
= 1/3hr
= 20mins
4.Average cost due to waiting on the part of the type writer per day
= 8*(1-(5/8))*1.5
= Rs4.5
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.