A company has just negotiated a contract to produce a part for another firm. In
ID: 408710 • Letter: A
Question
A company has just negotiated a contract to produce a part for another firm. In the process of manufacturing the part, the inside diameter of successive parts becomes smaller and smaller as the cutting tool wears. However, the specs are so wide relative to machine capabilities that it is possible to set the diameter initially at a large value and let the process run for a while before replacing the cutting tool The inside diameter decreases at an average rate of.001 cm per part, and the process has a standard deviation of.05 cm. The variability is approximately normal Assuming a three-sigma buffer at each end, how frequently must the tool be replaced if the process specs are 3 cm and 3 5 cm. Use (Number of shafts) n = 1. Determine how many pieces can be produced before the LCL just crosses the lower tolerance of 3 cm. (Do not round your intermediate calculations.)Explanation / Answer
Answer:
3-sigma = 3 x .02 cm (sigma) = .06 cm
To get the start process mean we subtract 3-sigma from the Upper spec and add 3-sigma to the lower spec:
15.0 cm + .06 cm = 15.06 cm (start process mean)
15.2 cm - .06 cm = 15.14 cm (end process mean)
Parts before replacement = (End Mean - Start Mean) / Wear Rate
(15.14 cm - 15.06 cm) / .004 cm = 20 cm
20 parts can be produced by this process before the tool must be replaced.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.