Question
This is a Project Management course. Explain question 2
| College Degree eText-1181[BERKCLMBA6 Page 47, Contemporary . A https://berkeley courseload.com/#/content.37es/address/t2 Project teria &Criteria1; Cniteria 2 Critena 3 Weighted Weight10 4 Total Score Project A 3 Project B Project C Project D 2. Complete the following scoring model. Show all your work. Tell which project you would pick first, second, third, and last. How confident are you with each choice? If you lack confidence regarding any of your choices, what would you prefer to do about it?Explanation / Answer
Weighted total score for project A = 4 * 10 + 3 * 6 + 5 * 4
Weighted total score for project A = 78
Weighted total score for project B = 3 * 10 + 2 * 6 + 3 * 4
Weighted total score for project B = 54
Weighted total score for project C = 2 * 10 + 4 * 6 + 3 * 4
Weighted total score for project C = 56
Weighted total score for project D = 1 * 10 + 3 * 6 + 4 * 4
Weighted total score for project D = 44
The project I would pick is project A because it has the highest weighted total score compared to other projects.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.