Group 4 Information on six projects are given below. You are required: To select
ID: 410230 • Letter: G
Question
Group 4
Information on six projects are given below. You are required:
To select the best one using a multi-weighted scoring model
To calculate implementation time and to prepare resources plans for the selected project
To recommend a strategy to reduce implementation time for the selected project.
Project activity
Precedent activity
Time (week)
Labour (person/ week)
Machine (unit/ week)
Cost (Millions VND/week)
Project 1
A
None
2
6
4
20
B
None
3
8
6
36
C
None
5
10
6
45
D
A
6
18
7
50
E
D
8
26
8
80
F
D
4
45
12
150
G
D
3
60
10
180
H
C, E
2
15
4
100
I
G
1
12
2
30
Project 2
A
None
2
6
4
20
B
None
3
8
6
36
C
A
5
10
6
45
D
A
6
18
7
50
E
A
8
26
8
80
F
A
4
45
12
150
G
B, C
3
60
10
180
H
F, G
2
15
4
100
I
D
1
12
2
30
Project 3
A
None
2
6
4
20
B
None
3
8
6
36
C
B
5
10
6
45
D
B
6
18
7
50
E
A, C
8
26
8
80
F
A, C
4
45
12
150
G
A, C
3
60
10
180
H
D, G
2
15
4
100
I
E
1
12
2
30
Project activity
Precedent activity
Time (week)
Labour (person/ week)
Machine (unit/ week)
Cost (Millions VND/week)
Project 4
A
None
2
6
4
20
B
None
3
8
6
36
C
None
5
10
6
45
D
A
6
18
7
50
E
B, D
8
26
8
80
F
B, D
4
45
12
150
G
B, D
3
60
10
180
H
C, E
2
15
4
100
I
G
1
12
2
30
Project 5
A
None
2
6
4
20
B
None
3
8
6
36
C
A
5
10
6
45
D
A
6
18
7
50
E
A
8
26
8
80
F
A
4
45
12
150
G
B, C
3
60
10
180
H
F, G
2
15
4
100
I
E, H
1
12
2
30
Project 6
A
None
2
6
4
20
B
None
3
8
6
36
C
None
5
10
6
45
D
A
6
18
7
50
E
C
8
26
8
80
F
C
4
45
12
150
G
B, D, E
3
60
10
180
H
B, D, E
2
15
4
100
I
F, H
1
12
2
30
Criteria Weight
ROI
Stay with core competencies
Defect reduction
Sale improvement
Customer loyalty improvement
Environmental friendly
0.25
0.1
0.3
0.2
0.1
0.05
Project 1
10
6
8
7
9
8
Project 2
7
9
6
8
8
7
Project 3
10
8
7
9
9
8
Project 4
8
8
9
6
7
6
Project 5
9
9
6
8
8
9
Project 6
6
8
9
8
6
6
Project activity
Precedent activity
Time (week)
Labour (person/ week)
Machine (unit/ week)
Cost (Millions VND/week)
Project 1
A
None
2
6
4
20
B
None
3
8
6
36
C
None
5
10
6
45
D
A
6
18
7
50
E
D
8
26
8
80
F
D
4
45
12
150
G
D
3
60
10
180
H
C, E
2
15
4
100
I
G
1
12
2
30
Project 2
A
None
2
6
4
20
B
None
3
8
6
36
C
A
5
10
6
45
D
A
6
18
7
50
E
A
8
26
8
80
F
A
4
45
12
150
G
B, C
3
60
10
180
H
F, G
2
15
4
100
I
D
1
12
2
30
Project 3
A
None
2
6
4
20
B
None
3
8
6
36
C
B
5
10
6
45
D
B
6
18
7
50
E
A, C
8
26
8
80
F
A, C
4
45
12
150
G
A, C
3
60
10
180
H
D, G
2
15
4
100
I
E
1
12
2
30
Explanation / Answer
1. Weighted score for projects
Project 1 : 10x0.25+ 6x0.1+ 8x0.3+ 7x0.2 + 9x0.1+ 8x0.05 = 8.2
Similarly
Project 2 : 7.2
Project 3 : 8.5
Project 4 : 7.7
Project 5 : 7.8
Project 6: 7.5
Project 3 should be selected, score being highest.
Ans 2: As it is seen BCEI is the critical path with duration of 17 days, which is the least time in which the project can be completed.
Ans 3 : The implementation time can be reduced by crashing the activities B, C or E to the minimum possible duration. E can be crashed for 3 days without critical path being changed. If it crashes for more than 3 days, F and G will also need to be crashed to keep BCEI as critical path.