Group 4 Information on six projects are given below. You are required: To select

ID: 410230 • Letter: G

Question

Group 4

Information on six projects are given below. You are required:

To select the best one using a multi-weighted scoring model

To calculate implementation time and to prepare resources plans for the selected project

To recommend a strategy to reduce implementation time for the selected project.

Project activity

Precedent activity

Time (week)

Labour (person/ week)

Machine (unit/ week)

Cost (Millions VND/week)

Project 1

A

None

2

6

4

20

B

None

3

8

6

36

C

None

5

10

6

45

D

A

6

18

7

50

E

D

8

26

8

80

F

D

4

45

12

150

G

D

3

60

10

180

H

C, E

2

15

4

100

I

G

1

12

2

30

Project 2

A

None

2

6

4

20

B

None

3

8

6

36

C

A

5

10

6

45

D

A

6

18

7

50

E

A

8

26

8

80

F

A

4

45

12

150

G

B, C

3

60

10

180

H

F, G

2

15

4

100

I

D

1

12

2

30

Project 3

A

None

2

6

4

20

B

None

3

8

6

36

C

B

5

10

6

45

D

B

6

18

7

50

E

A, C

8

26

8

80

F

A, C

4

45

12

150

G

A, C

3

60

10

180

H

D, G

2

15

4

100

I

E

1

12

2

30




Project activity

Precedent activity

Time (week)

Labour (person/ week)

Machine (unit/ week)

Cost (Millions VND/week)

Project 4

A

None

2

6

4

20

B

None

3

8

6

36

C

None

5

10

6

45

D

A

6

18

7

50

E

B, D

8

26

8

80

F

B, D

4

45

12

150

G

B, D

3

60

10

180

H

C, E

2

15

4

100

I

G

1

12

2

30

Project 5

A

None

2

6

4

20

B

None

3

8

6

36

C

A

5

10

6

45

D

A

6

18

7

50

E

A

8

26

8

80

F

A

4

45

12

150

G

B, C

3

60

10

180

H

F, G

2

15

4

100

I

E, H

1

12

2

30

Project 6

A

None

2

6

4

20

B

None

3

8

6

36

C

None

5

10

6

45

D

A

6

18

7

50

E

C

8

26

8

80

F

C

4

45

12

150

G

B, D, E

3

60

10

180

H

B, D, E

2

15

4

100

I

F, H

1

12

2

30

Criteria                Weight

ROI

Stay with core competencies

Defect reduction

Sale improvement

Customer loyalty improvement

Environmental friendly

0.25

0.1

0.3

0.2

0.1

0.05

Project 1

10

6

8

7

9

8

Project 2

7

9

6

8

8

7

Project 3

10

8

7

9

9

8

Project 4

8

8

9

6

7

6

Project 5

9

9

6

8

8

9

Project 6

6

8

9

8

6

6

Project activity

Precedent activity

Time (week)

Labour (person/ week)

Machine (unit/ week)

Cost (Millions VND/week)

Project 1

A

None

2

6

4

20

B

None

3

8

6

36

C

None

5

10

6

45

D

A

6

18

7

50

E

D

8

26

8

80

F

D

4

45

12

150

G

D

3

60

10

180

H

C, E

2

15

4

100

I

G

1

12

2

30

Project 2

A

None

2

6

4

20

B

None

3

8

6

36

C

A

5

10

6

45

D

A

6

18

7

50

E

A

8

26

8

80

F

A

4

45

12

150

G

B, C

3

60

10

180

H

F, G

2

15

4

100

I

D

1

12

2

30

Project 3

A

None

2

6

4

20

B

None

3

8

6

36

C

B

5

10

6

45

D

B

6

18

7

50

E

A, C

8

26

8

80

F

A, C

4

45

12

150

G

A, C

3

60

10

180

H

D, G

2

15

4

100

I

E

1

12

2

30

Explanation / Answer

1. Weighted score for projects

Project 1 : 10x0.25+ 6x0.1+ 8x0.3+ 7x0.2 + 9x0.1+ 8x0.05 = 8.2

Similarly

Project 2 : 7.2

Project 3 : 8.5

Project 4 : 7.7

Project 5 : 7.8

Project 6: 7.5

Project 3 should be selected, score being highest.

Ans 2: As it is seen BCEI is the critical path with duration of 17 days, which is the least time in which the project can be completed.

Ans 3 : The implementation time can be reduced by crashing the activities B, C or E to the minimum possible duration. E can be crashed for 3 days without critical path being changed. If it crashes for more than 3 days, F and G will also need to be crashed to keep BCEI as critical path.