The purchasing manager for Alpa Enterprises requested the following data from th
ID: 410341 • Letter: T
Question
The purchasing manager for Alpa Enterprises requested the following data from the accounting department: Annual demand = 15,500; Cost of placing an order = £180; Annual inventory holding costs = 20 percent; Unit cost = £78Assume Alpha’s demand for an item during the lead time is normally distributed with a mean of 5,000 and a standard deviation of 50. What reorder point should be used in order to average no more than one stock out every 20 re-order cycles? If safety stock is 70, how often will a stock out occur during a re-order cycle? The purchasing manager for Alpa Enterprises requested the following data from the accounting department: Annual demand = 15,500; Cost of placing an order = £180; Annual inventory holding costs = 20 percent; Unit cost = £78
Assume Alpha’s demand for an item during the lead time is normally distributed with a mean of 5,000 and a standard deviation of 50. What reorder point should be used in order to average no more than one stock out every 20 re-order cycles? If safety stock is 70, how often will a stock out occur during a re-order cycle? The purchasing manager for Alpa Enterprises requested the following data from the accounting department: Annual demand = 15,500; Cost of placing an order = £180; Annual inventory holding costs = 20 percent; Unit cost = £78
Assume Alpha’s demand for an item during the lead time is normally distributed with a mean of 5,000 and a standard deviation of 50. What reorder point should be used in order to average no more than one stock out every 20 re-order cycles? If safety stock is 70, how often will a stock out occur during a re-order cycle?
Explanation / Answer
Target stockout is one stock out in 20 reorder cycles
Thus, probability of stockout = 1/ 20 = 00.05
Thus, in stock probability = 1 – 0.05 = 0.95
Corresponding Z value for in stock probability of 0.95 = NORMSINV ( 0.95) = 1.6448
Therefore, safety stock = Z value x Standard deviation of demand during lead time = 1.6448 x 50 = 82.24 ( 82 rounding to nearest whole number)
Thus, reorder point = Demand during lead time + safety stock = 5000 + 82 = 5082
REQUIRED REORDER POINT = 5082
If safety stock = 70 , Standard deviation of demand during lead time = 50 and corresponding Z value = Z1
Then
Safety stock = Z value x Standard deviation of demand during lead time
Or, 70 = Z1 x 50
Or, Z1 = 70/50 = 1.4
Corresponding value of probability for Z1 = 1.4 as derived from standard normal distribution table 0.91924
Thus in stock probability = 0.91924
Thus probability of stock out during reorder cycle = 1 – 0.91924 = 0.08076 or 8.076 % times
STOCKOUT WILL OCCUR APPROX 8.076% PERCENTAGE OF TIME DURING A REORDER CYCLE
REQUIRED REORDER POINT = 5082
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.