When can we conclude that an activity has an 'acceptable level of risk?' a. If it can be determined that the probability of harm involved in a specific work activity is manageable. b. If the probability of harm involved in a specific work activity is acceptable by insurance and workers' compensation laws. c. If it can be determined that the probability of harm involved in a specific work activity is equal to or less than the probability of harm of some more common activity. d. If the employers are willing to compensate the harm caused to workers for a specific activity.
Explanation / Answer
Ans: C - If it can be determined that the probability of harm involved in a specific work activity is equal to or less than the probability of harm of some more common activity.
Acceptable level of risk is being determined by the manage.ment level of risk and impact of that activity. Activity which fall under the security level where threat will not be imminent or can be controlled by the security department of company. A threat to security can posses harm to business and could lower the reputation so it would be essential to maintain the acceptable level risk by the security
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.