experiences a learning rate of 80%. At a labor rate of $35 per hour, what should

ID: 415090 • Letter: E

Question

experiences a learning rate of 80%. At a labor rate of $35 per hour, what should you, as the purchasing agent, ex- pect to pay for the fifth unit? 8.9 Problem 8 identified how long it should take to complete the fifth oil-drilling platform that Natural Resources plans to purchase. How long should all five oil-drilling rigs take to complete? 8.8 It took MegaTech, Inc., 100,000 labor-hours to produce the first of several oil-drilling rigs for Antarctic explora- tion. Your company, Natural Resources, Inc., has agreed to purchase the fifth (steady state) oil-drilling rig from MegaTech's manufacturing vard. Assume that MegaTech

Explanation / Answer

We will use Learning curve table to solve this problem

Answer to question 8.8 :

Time taken to produce 1st unit = 100,000 labor hours

Learning rate = 80%

Thus, Time required to produce 5th unit ( using standard learning curve table ) = 59563.73 hours

Amount purchasing agent expected to pay for 5th unit = $35/hour x 59563.73 hours = $2084730.55

Answer to question 8.9 :

As per Learning curve, total time taken by all 5 oil drilling rigs to complete = 373774.10 hours