(Process Analysis with One Product) Consider a process consisting of three stati
ID: 415361 • Letter: #
Question
(Process Analysis with One Product) Consider a process consisting of three stations (Station 1 comes first, followed by Station 2 and then Station 3): 1. Station 1 2 Processing Time [Min./Unit] 6 4 10 Number of Machines 2 2 Assuming 100% machine availability and 100% yield, answer the following questions: (a) which station(s) is the bottleneck of the system? what is the process capacity (measured in # units/hour)? (b) If demand is 18 units per hour, what is the output rate of the process, and what is the utilization of each station?Explanation / Answer
Answer to question #a :
Effective process capacity of any station = Processing time / Number of machines
Thus,
Effective Process capacity of Station 1 = 6/2 = 3 minutes / unit
Effective process capacity of Station 2 = 4/ 2 = 2 minutes/ unit
Effective process capacity of station 3 = 10/3 = 3.33 minutes/ unit
Since , Station 3 has the highest processing time/ unit, this is the bottleneck station of the system.
Process capacity of a system is determined by the processing capacity of bottleneck process .
Therefore, it can be concluded that cycle time of the system is 3.33 minutes/ unit.
Therfore, Process Capacity of the system = 60 / 3.33 = 18 units / hour
PROCESS CAPACITY IS 18 UNITS/ HOUR
Answer to question # b:
Output rate of a process can be defined as :
Output rate = Demand per hour / Process capacity per hour x 100 = 18/18 x 100 = 100 %
Output capacity of station 1 = 60 minutes / 3 minutes = 20 per hour
Output capacity of station 2 = 60 minutes / 2 minutes = 30 per hour
Output capacity of station 3 = 60 minutes /3.33 = 18 per hour
Utilization of each station can be defined as :
Utilization of any station = Demand per hour of 18 units/ Output capacity of station x 100
Thus,
Utlization of Station 1 = 18/20 x 100 =90%
Utlization of station 2 = 18/30 x 100 = 60%
Utilization of station 3 =18/18 x 100 = 100 %