Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

I do not need the solution for the first Schedule I need the solution for the se

ID: 420491 • Letter: I

Question

I do not need the solution for the first Schedule I need the solution for the second Schedule

In the following MRP planning schedule tor Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week (Leave no cells blank- be certain to enter "o" wherever required.) EK NUMBER ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 75 50 70 40 Period Gross requirements 50 70 Item J Scheduled OH:40 Projected available balance LT = 1 SSNet requirements Q L4L Planned order receipts receipts Planned order releases Hints References Hint #1 Show allx 217 AM ^ media%2F161%2F."jpg Type here to search

Explanation / Answer

Following data are provided :

Ordering pattern = Lot for Lot ( L4L)

On hand quantity ( OH ) = 40

Lead time = 1 week

Following to be noted :

Net requirement for period t > Gross requirement for period t – Projected available balance for period t-1

Please refer below table for relevant data derived as per above explanations :

Period

1

2

3

4

5

Gross requirement

0

75

0

50

70

Scheduled receipts

0

0

0

0

0

Projected available balance ( On hand = 40)

40

0

0

0

0

Net requirement

0

35

0

50

70

Planned order receipt

0

35

0

50

70

Planned order release

35

0

50

70

0

Period

1

2

3

4

5

Gross requirement

0

75

0

50

70

Scheduled receipts

0

0

0

0

0

Projected available balance ( On hand = 40)

40

0

0

0

0

Net requirement

0

35

0

50

70

Planned order receipt

0

35

0

50

70

Planned order release

35

0

50

70

0

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at drjack9650@gmail.com
Chat Now And Get Quote