Direct Labor Variances The following data relate to labor cost for production of
ID: 422636 • Letter: D
Question
Direct Labor Variances
The following data relate to labor cost for production of 6,800 cellular telephones:
a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
b. The employees may have been less-experienced or poorly trained, thereby resulting in a lower labor rate than planned. The lower level of experience or training may have resulted in less efficient performance. Thus, the actual time required was more than standard.
Actual: 4,600 hrs. at $14.4 Standard: 4,530 hrs. at $14.6Explanation / Answer
Actual Hours worked= 4,600 hrs.
Actual Rate per Hour = $14.4
Standard Hours worked = 4,530 hrs. at
Standard Rate per Hour =$14.6
We have three costs:
Direct Labor Rate Variance
= Actual cost incurred - Actual Hours of Input, at the Standard Rate
= (Actual Rate per Hour * Actual Hours) – (Standard Rate per Hour × Actual Hours)
= (Actual Rate per Hour – Standard Rate per Hour) × Actual Hours
= ($14.4 – $14.6) × 4600 hrs
= - 920
Favorable (actual cost incurred I paid is less than what I would have paid at standard rate)
Labor time variance
= (Actual hours worked -Standard hours allowed) × Standard rate
= (Actual hours worked × Standard rate)-(Standard hours allowed× Standard rate)
= (4600-4530)*14.6
=1022
Unfavorable
The actual hours I have put in (at standard rate) is more than the budgeted amount
Total direct labor cost variance:
= Direct Labor Rate Variance + Direct Labor time variance
=1022 (unfavorable) + -920 (favorable)
=102
Here unfavorable variance is greater than favorable. Hence the variance is taken as unfavorable
Another method for easy understanding
Total direct labor cost variance:
= Actual cost -Standard cost
= Actual cost incurred - Standard cost /budgeted cost
= (AH × AR) - (SH × SR) =
= 66240-66138
=102
Actual cost incurred is greater than budgeted cost. Variance unfavorable
b.Actual labor rate per hour is lower than budgeted one resulting in rate variance
Employees may have less-experienced or poor training. so their efficiency is low resulting in time variance or effcefficiencyaiance
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.