1. In resource leveling, or smoothing, levels the resources so that: equal numbe
ID: 423910 • Letter: 1
Question
1. In resource leveling, or smoothing, levels the resources so that: equal number of resources is assigned to each task. an equal number of tasks are completed each day by the resources on the project. they are applied as uniformly as possible without extending the project schedule beyond the required completion time the costs for the resources are even as possible across the project. A. B. C. D. When several activities need the same limited resource at the same time, the activities with A. the least slack have first priority. B. the longest duration have first 2. C. the near term have first priority. D. use the most resources have first priority priority. 3. includes determining which risks may adversely affect the project objective and what the impact of each risk might be if it occurs A. Risk modification B. Risk avoidance C. Risk identification D. Risk acceptance . Waiting for unfavorable events to occur and then reacting to them is a cost saving measure by not planning. is part of a well-designed response plan. reflects much planning and consideration of consequences. A. C. B. D. can result in panic and costly responsesExplanation / Answer
1. C. they are applied as uniformly as possible without extending the project schedule beyond the required completion time.
2. A. the least slack have first priority
3. C. Risk identification
4. D. can result in panic and costly responses.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.