Score: 0 of 1 pt 8 of 11 (6 complete) HW Score: 44.42%, 4.89 of 11 pts Problem 15.11- Bookmatch Question Help Calculate the Critical Ratios (CR): (Enter al responses rounded to two decimal places.) The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Job CR Duration (days) Job 103 205 309 412 517 103 Due Date 223 217 219 217 15 Assume that all jobs arrived on day 180; today's date is 200 Enter your answer in the answer box and then click Check Answer parts remaining Clear All Check AnswerExplanation / Answer
Job
Processing Time? (days)
Due Date ?(days from now)
Slacking time
Critical ratio
103
10
14
4
1.4
214-200
Due date/Processing Days
Job
Processing Time? (days)
Due Date ?(days from now)
Slacking time
Critical ratio
103
10
14
4
1.4
214-200
Due date/Processing Days
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.