6. Which of the following is a similarity between scope control and schedule con

ID: 425737 • Letter: 6

Question

6. Which of the following is a similarity between scope control and schedule control? a. Both are initial processes of project time management. b. Both of their primary goals is to define project goals and milestones . Both are portions of the integrated change control process under project integration management d. Both of these processes should occur before estimating activity durations. 7. are those costs that are difficult to measure in monetary terms. a. Intangible costs c. Tangible costs b. Direct costs d. Fixed costs

Explanation / Answer

6. C. both are portions of the integrated change control process under project integration management.

7. A. intangible cost

8. C. electricity used to run its factories

9. A. they allow for future situations that can be partially planned for

10. C. they are most reliable when previous projects are similar in fact to the current projects.