(5a). At a bank, the tellers on average take 11 minutes per customer, with a sta
ID: 426417 • Letter: #
Question
(5a). At a bank, the tellers on average take 11 minutes per customer, with a standard deviation of 9 minutes. What is the coefficient of variation of the service time? (Provide the answer as a decimal number, not a percentage; provide two significant digits to the right of the decimal point) (b). A project has seven activities - A, B, C, D, E, F, and G. They have mean activity times of 12, 15, 18, 9, 14, 10, and 8 days respectively, and each of them have a standard deviation of 2 days. The critical path has been identified as B-E-F- G. What is the standard deviation of the project completion time?Explanation / Answer
(5a) Coefficient of variation of service time
= Standard deviation / Mean service time
= 9/11
= 0.82
(b)
Variance of the project completion time
= Sum of variances of critical activities (Variance is the square of standard deviation)
= 22+22+22+22 = 16
Standard deviation of the project completion time
= Square root of variance
= SQRT(16)
= 4