Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The demand for subassembly S is 110 units in week 7. Each unit of S requires 1 u

ID: 427971 • Letter: T

Question

The demand for subassembly S is 110 units in week 7. Each unit of S requires 1 unitnothing of T and 2 unitss of U. Each unit of T requires 2 unitss of? V, 1 unitnothing of? W, and 2 unitss of X.? Finally, each unit of U requires 2 unitss of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make? S, 1 week nothing to make? T, 2 weeks to make? U, 2 weekss to make? V, 3 weeks to make? W, 2 weekss to make? X, 2 weeks to make? Y, and 2 weekss to make Z. Construct a gross material requirements plan ?(type 0 if the input box is not? used).

Explanation / Answer

Gross material requirements plan is following

Gross requirement = Gross requirement of parent item * Usage per parent item.

Item Parent Item Usage per Parent Lead Time (weeks) Gross Requirement When required (week) Order Start (week) S 2 110 11 9 T S 1 1 110 9 8 U S 2 2 220 9 7 V T 2 2 220 8 6 W T 1 3 110 8 5 X T 2 2 220 8 6 Y U 2 2 440 7 5 Z U 3 2 660 7 5
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote