You are preparing a project to lay fiber optic cable. The first task is to mobil
ID: 429317 • Letter: Y
Question
You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable. This will take three weeks and will cost $45,000. The total length of the cable is 15 miles. The last task, which will take one week, is to Terminate and test the cable. You budget $5000 for this. At the end of the first week, you have completed mobilization, but it cost a total of $4500. At the end of the third week, you have completed five miles of cable at a total cost of $28,000 (installation only). It takes you a total of 10 weeks to complete the entire project, for a total cost of $65,000.
At the end of week 1:
i.What is your SPI?
ii.What is your CPI?
iii.What is your EAC?
At the end of week 3:
i.What is your SPI?
ii.What is your CPI?
iii.What is your EAC?
At the end of the project:
i.What is your SPI?
ii.What is your CPI?
iii.What is your EAC?
Explanation / Answer
At the end of week -1
SPI = EV/PV
EV = PV = $3000
SPI = 1
CPI = EV/AC
= 3000/4500 = 0.67
EAC = BAC/CPI = 3000/0.67 = $ 4500
At the end of 3rd week:
PV = $45000
EV = (5/15)*45000 = $15000
SPI = EV/PV = 15000/45000 = 0.33
CPI = EV/AC = 15000/28000 = 0.54
EAC = BAC/CPI = 45000/0.54 = $84000
End of Project:
SPI =1
CPI= (3000+45000+5000)/65000 = 0.82
EAC = BAC/CPI = (53000)/0.82 = $65000