An appliance assembly activity is to be done by robots and the precedence diagra
ID: 431287 • Letter: A
Question
An appliance assembly activity is to be done by robots and the precedence diagram has nine steps as shown, with element times in minutes. and an output of 20 pts 3) 7 hrs /day. The assembly line operates continuously 512 units per day is desired. a) Compute the optimum cycle time, CT = b) What is the minimum number of robots? c) Group the activities into an appropriate number of work stations(ist your groups). How many stations are needed? d) What is the balance efficiency of your arrangement based on actual cycle times? 0.29 min. Dril Holes 0.42 min. Allign frame 0.74 min. Set speed 0.34 min ck up frame 0.49 min. Install switch 0.51 min. Package 0.30 min. 0.40 min. Electrical check Install Motor 0.40 min. Connect MotorExplanation / Answer
1. current cycle time is- 5 min 19 seconds
(0.34+0.42+0.29+0.49+0.74+0.40+0.51)= 319 seconds
it is the longest duration in this path
if you prefers to shortest path, then = 0.34+0.30+0.40+ 0.74+0.40+ 0.51= 269 seconds
2. the minimum number of robots used are 7 robots
3. the total 7 works can be grouped under 5 heads of works
4. the balanced efficiency is- 5.19 minutes
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.