12. Which of the following is a major source of data for the material requiremen

ID: 432597 • Letter: 1

Question

12. Which of the following is a major source of data for the material requirements plan?

a. Route file

b. Master production schedule

c. Demand forecasts

d. Capacity requirement plan

13. To find out the types of components in a clock radio, you would look at which of the following?

a. Bill of material

b. Routing sheet

c. Resource requirements plan

d. Master production schedule

14. If you wanted to know the operation(s) that would be performed on a particular component at a specific workstation, you would look on which of the following?

a. Bill of material

b. Master production schedule

c. Route sheet

Inventory status

d. Any of the above

e. Any of the apove

5 . Which of the following is an advantage of using a lateral supply chain?

a. To improve business focus and expertise

b. To leverage communication and production competencies

c. To achieve economies of scale and scope

d. All of the above

6. True or false? The three Vs are velocity, visibility, and volume.

     _____True

     _____False

7. True or false? One of the benefits of supply chain management is increased visibility of flows.

   _____True

    _____False

8. Organizational design does not refer to

a. the framework within which operational and management activities are performed.

b. how internal and external communication flows.

c. an organizational structure to support strategic business plans and goals.

d. how employees view the structure of a company.

9. Which of the following is the supply chain evolution stage in which a nucleus company begins initiatives to improve efficiency, effectiveness, and quality within functional areas?

a. Multiple dysfunction

b. Semi functional enterprise

c. Integrated enterprise

d. Extended enterprise

Explanation / Answer

Question:- Which of the following is a major source of data for the material requirements plan?

Answer:- Master production schedule

Reason:= MPS is used by material requirements plan to determine the number of parts required to produce the product

Question:- To find out the types of components in a clock radio, you would look at which of the following?

Answer:- Bill of material

Reason- Bill of material is provides an input about the raw materials, assemblies, subassemblies, parts and components, along with the quantities of each which is required to produce a product

Question:- if you wanted to know the operation(s) that would be performed on a particular component at a specific workstation, you would look on which of the following?

Answer:- Route sheet

Reason:- Route sheet is a document which provides the information about the processes to be performed on the material