Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The table provides a project with the task lengths (in days) and precedence requ

ID: 432943 • Letter: T

Question

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates. Task Length Predecessor Optimistic Most Likely Pessimistic A 7 — 6.1 7 7.5 B 4 A 2.5 4 6 C 8 A 6.7 8 8.75 D 3 B, C 2 3 4.5 E 2 B 1.5 2 2.3 F 8 D, E 7.3 8 8.7 Based on the information, which of the following statements is true? None of the paths in the project is a critical path. Path ABEF is the critical path for the project. Path ABDF is the critical path for the project. Path ACDF is the critical path for the project. Tasks A, B, C, D, and F lie in the critical path for the project.

Explanation / Answer

The precedence diagram of activities as follows :

                                                                                                        A

                                                                               B

C

E

                                    D

                                                                                            F

Following table presents expected duration of each activity. It is to be noted that Expected duration of each activity = ( Optimistic + 4 x Most likely + Pessimistic) / 6

Task

Predecessor

Optimistic(O)

Most likely(M)

Pessimistic(P)

Expected Duration ( O + 4.M + P/6)

A

None

6.1

7

7.5

6.93

B

A

2.5

4

6

4.08

C

A

6.7

8

8.75

7.91

D

B,C

2

3

4.5

3.08

E

B

1.5

2

2.3

1.97

F

D,E

7.3

8

8.7

8.00

On basis of above precedence diagram and the table for expected durations of each activity . the possible parallel paths and their corresponding expected durations as follows :

A-B-E-F = 6.93 + 4.08 + 1.97 + 8 = 20.98

A-B-D-F = 6.93 + 4.08 + 3.08 + 8 = 22.09

A-C-D-F = 6.93 + 7.91 + 3.08 + 8 = 25.92

Out of above, since A-C-D-F has the longest duration, it is the critical path .

PATH A-C-D-F IS THE CRITICAL PATH FOR THE PROJECT

                                                                                                        A

                                                                               B

C

E

                                    D

                                                                                            F

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote