The Department of Transportation has found that a proposed highway project is no

ID: 434327 • Letter: T

Question

The Department of Transportation has found that a proposed highway project is not going to be completed before the end of the summer. They have asked the contractor to prepare cost figures to shorten the project by up to 4 weeks.


The following table shows the Crashing Costs for each activity. For example, if you needed to shorten Activity 1-2 by 1 week this would cost $12. If you needed to shorten the same activity by 2 weeks it would cost $16. Note: If an activity lists a cost of $---, then this activity cannot be any shorter.

Activity

First Week

Second Week

Third Week

1-2

$12

$16

$ ---

2-5

6

8

10

5-7

7

8

11

7-11

7

11

---

11-13

4

8

10

1-3

12

14

19

3-8

5

---

---

8-11

12

13

14

3-9

14

16

16

9-12

8

8

10

12-13

7

11

---

1-4

10

14

18

4-6

12

14

18

6-10

11

12

---

10-12

14

15

---





The Current Length of the Project is

weeks.


Determine the costs to shorten the project.


1st Week Cost =

Hint: Between 2 and 7
2nd Week Cost =


3rd Week Cost =


4th Week Cost =

Hint: Between


Note: For each week you are to include only the cost of shortening the activities in that particular week.

Save

Activity

First Week

Second Week

Third Week

1-2

$12

$16

$ ---

2-5

6

8

10

5-7

7

8

11

7-11

7

11

---

11-13

4

8

10

1-3

12

14

19

3-8

5

---

---

8-11

12

13

14

3-9

14

16

16

9-12

8

8

10

12-13

7

11

---

1-4

10

14

18

4-6

12

14

18

6-10

11

12

---

10-12

14

15

---

5 10 13 10 12

Explanation / Answer

The current length of the project is 41 weeks.

1st-week crash

Crash activity 11-13 with a crash cost of $4.

2nd-week crash

Note that two critical paths (1-3-8-11-13 and 1-3-9-12-13) have emerged. Crash activity 11-13 by one week with a crash cost of $12.

3rd-week crash

Note that three critical paths have emerged. Crash activities 2-5, 3-8, and 12-13 with a total cost of crashing equal to 6+5+7 = $18.

4th-week crash

Still, there are three critical paths. Crash activity 11-13 and 9-12 for a crashing cost of 8+8 = $16.

Project path Duration 1-2-5-7-11-13 40 1-3-8-11-13 41 1-3-9-12-13 40 1-4-6-10-12-13 38