45. CP is determined based on 1. Longest path 2. Shortest path 3. Average path 4
ID: 434449 • Letter: 4
Question
45. CP is determined based on 1. Longest path 2. Shortest path 3. Average path 4. Final path 46. EPC indicates mainly needed: 1. Entertainment sites 2. Restaurants 3. Cruises for top management 4. All the above 5. None of the above 47. SME loans are determined based on: 1. EPC 2. Budget 3. Itemized cost 4. All the above None of the above 5. 48. J-shape lifecycle is mainly used with 1. High quality products 2. Limited number of products 3. Samples not actual product 4. All the above 5. None of the above 49. SME may: 1. 2. 3. Combine controlling departments Never combine controlling departments Cancel controlling departments 4. Outsource all departments 50. SME sustainability may skip: 1. Job satisfaction 2. Training 3. EOE/equity/fairness 4. All the above 5. None of the aboveExplanation / Answer
Answering the first 4 questions:
45. CP is determined based on longest path.
Answer: Option 1
46. EPC indicates mainly needed for all of the above
Answer: Option 4
47. SME loans are determined based on all of the above
Answer: Option 4
48. J-shaped lifecycle is mainly used for limited number of products
Answer: Option 2
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.