The Barberton Municipal Division of Road Maintenance is charged with road repair

ID: 435037 • Letter: T

Question

The Barberton Municipal Division of Road Maintenance is charged with road repair in the city of Barberton and the surrounding area. Cindy Kramer, road maintenance director, must submit a staffing plan for the next year based on a set schedule for repairs and on the city bud- get. Kramer estimates that the labor hours required for the next four quarters are 6,000, 12,000, 19,000, and 9,000 respectively. Each of the 11 workers on the workforce can contribute 500 hours per quarter. Payroll costs are $6,000 in wages per worker for regular time worked up to 500 hours, with an overtime pay rate of $18 for each overtime hour. Overtime is limited to 20 percent of the regular-time capacity in any quarter. Although unused overtime capacity has no cost, unused regular time is paid at $12 per hour. The cost of hiring a worker is $3,000, and the cost of laying off a worker is $2,000. Subcontract- ing is not permitted. a. Find a level workforce plan that relies just on overtime and the minimum amount of undertime possible. Overtime can be used to its limits in any quarter. What is the total cost of the plan and how many undertime hours does it call for? b. Use a chase strategy that varies the workforce level without using overtime or undertime. What is the total cost of this plan? Propose a plan of your own. Compare your plan with those in part (a) and part (b) and discuss its compara- c.

Explanation / Answer

Answer A:-

   Quarter

1

2

3

4

Total

Forecasted demand (hrs)

6,000

12,000

19,000

9,000

46,000

Workforce level (workers)

12

24

37

18

91

Undertime (hours)

240

480

240

360

1,320

Overtime (hours)

0

0

0

0

0

Utilized time (hours)

6,000

12,000

19,000

9,000

46,000

Hires (workers)

1

12

13

0

26

Layoffs (workers)

0

0

0

19

19

What is the total cost of this plan?

Costs

Utilized time

$72,000

$144,000

$228,000

$108,000

$552,000

Undertime

2,880

5,760

2,880

4,320

15,840

Overtime

0

0

0

0

0

Hires

3,000

36,000

39,000

0

78,000

Layoffs

0

0

0

38,000

38,000

Total Cost =

$683,840

Answer B:-

Find a level-utilization plan for the Barberton Municipal Division that allows no delay in road repair and minimizes undertime. Overtime can be used to its limits in any quarter. Given that the demand peaks in quarter 3, we get:

                              1.20w = 19000/520 = 36.54 employee-period equivalents                     

                                     w = 30.45 or 31 employees

   Quarter

1

2

3

4

Total

Forecasted demand (hrs)

6,000

12,000

19,000

9,000

46,000

Workforce level (workers)

31

31

31

31

124

Undertime (hours)

10,120

4,120

0

7,120

21,360

Overtime (hours)

0

0

2,880

0

2,880

Utilized time (hours)

6,000

12,000

16,120

9,000

43,120

Hires (workers)

20

0

0

0

20

Layoffs (workers)

0

0

0

0

0

Quarter

1

2

3

4

Total

Forecasted demand (hrs)

6,000

12,000

19,000

9,000

46,000

Workforce level (workers)

12

24

31

18

85

Undertime (hours)

240

480

0

360

1,080

Overtime (hours)

0

0

2,880

0

2,880

Utilized time (hours)

6,000

12,000

16,120

9,000

43,120

Hires (workers)

1

12

7

0

20

Layoffs (workers)

0

0

0

13

13

Several solutions are possible. The key idea in creating this one is hiring only 7 employees in quarter 3, while using overtime to its maximum limit and eliminating undertime for that quarter. Hiring fewer in quarter 3 allows the number of layoffs in quarter 4 to drop to only 13, down from 19.

What is the cost of your mixed strategy plan?

Costs

Utilized time

$72,000

$144,000

$193,440

$108,000

$517,440

Undertime

2,880

5,760

0

4,320

12,960

Overtime

0

0

51,840

0

51,840

Hires

3,000

36,000

21,000

0

60,000

Layoffs

0

0

0

26,000

26,000

Total Cost =

$668,240

(students complete highlighted sections)
What is the cost of this level-utilization workforce plan?

Costs

Utilized time

$72,000

$144,000

$193,440

$108,000

$517,440

Undertime

121,440

49,440

0

85,440

256,320

Overtime

0

0

51,840

0

51,840

Hires

60,000

0

0

0

60,000

Layoffs

0

0

0

0

0

Total Cost =

$885,600

   Quarter

1

2

3

4

Total

Forecasted demand (hrs)

6,000

12,000

19,000

9,000

46,000

Workforce level (workers)

12

24

37

18

91

Undertime (hours)

240

480

240

360

1,320

Overtime (hours)

0

0

0

0

0

Utilized time (hours)

6,000

12,000

19,000

9,000

46,000

Hires (workers)

1

12

13

0

26

Layoffs (workers)

0

0

0

19

19