Question

Determine the critical path and project completion time. Select the critical? path(s) below. ?(Mark all that? apply.)

The following information concerns a project to raise money for the Kids Against Crime Foundation: Activity Activity Time (days Immediate Predecessor(s) A, B A, B A, B C, E C, D E, H I, J 12 a. Choose the correct network diagram below for this project. O A. b. Determine the critical path and project completion time. Select the critical path(s) below. (Mark all that apply.) A-D-G-H-J-K A-C-G-H-J-K All of the paths on the diagram are critical.

Explanation / Answer

a) C represents the correct figure.

b)

A-D-G-H-J-K = 9+4+5+11+10+12= 51

B-C-G-H-J-K = 11+9+5+11+10+12= 58

B-D-G-H-J-K = 11+4+5+11+10+12= 53

A-C-G-H-J-K= 9+9+5+11+10+12= 56

Hence the critical path and project completion time is 58 days