Determine the critical path and project completion time. Select the critical? pa
ID: 435477 • Letter: D
Question
Determine the critical path and project completion time. Select the critical? path(s) below. ?(Mark all that? apply.)
The following information concerns a project to raise money for the Kids Against Crime Foundation: Activity Activity Time (days Immediate Predecessor(s) A, B A, B A, B C, E C, D E, H I, J 12 a. Choose the correct network diagram below for this project. O A. b. Determine the critical path and project completion time. Select the critical path(s) below. (Mark all that apply.) A-D-G-H-J-K A-C-G-H-J-K All of the paths on the diagram are critical.Explanation / Answer
a) C represents the correct figure.
b)
A-D-G-H-J-K = 9+4+5+11+10+12= 51
B-C-G-H-J-K = 11+9+5+11+10+12= 58
B-D-G-H-J-K = 11+4+5+11+10+12= 53
A-C-G-H-J-K= 9+9+5+11+10+12= 56
Hence the critical path and project completion time is 58 days
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.