Crew size Average productivity per worker 2 2117 sq ft per day 3 1784 sq ft per

ID: 436485 • Letter: C

Question

Crew size                    Average productivity per worker

2                                     2117 sq ft per day

3                                     1784 sq ft per day

4                                      1965 sq ft per day

which crew size had highest productivity and which one lowest, give explanations for these results.

if a customer had a storm and her garden was ruined and the owner sends 4 workers even though 2 workers would have been higher productivity, explain his decision.

what is a possible qualitative issue that may very well influence productivity levels that the productivity ratios fail to take into account?

Explanation / Answer

Crew size                    Average productivity per worker Average productivity per worker per crew

2                                     2117 sq ft per day                       1058.5

3                                     1784 sq ft per day                        594.66

4                                      1965 sq ft per day                        491.25

crew size having highest productivity is 2 might be because better for job ,crew fitness ,dexterous crews , good combination

crew size having lowest productivity is 4 might be bacuase unfit for job , internal quarrels and unrhythemic work , unskilled

speaking qualitatively it may happen that being 4 member crew , their psycology towards will change and they might think its little work for 4 of them even though productivity is less ,first impact will as be psycological