Crew size Average productivity per worker 2 2117 sq ft per day 3 1784 sq ft per
ID: 436485 • Letter: C
Question
Crew size Average productivity per worker
2 2117 sq ft per day
3 1784 sq ft per day
4 1965 sq ft per day
which crew size had highest productivity and which one lowest, give explanations for these results.
if a customer had a storm and her garden was ruined and the owner sends 4 workers even though 2 workers would have been higher productivity, explain his decision.
what is a possible qualitative issue that may very well influence productivity levels that the productivity ratios fail to take into account?
Explanation / Answer
Crew size Average productivity per worker Average productivity per worker per crew
2 2117 sq ft per day 1058.5
3 1784 sq ft per day 594.66
4 1965 sq ft per day 491.25
crew size having highest productivity is 2 might be because better for job ,crew fitness ,dexterous crews , good combination
crew size having lowest productivity is 4 might be bacuase unfit for job , internal quarrels and unrhythemic work , unskilled
speaking qualitatively it may happen that being 4 member crew , their psycology towards will change and they might think its little work for 4 of them even though productivity is less ,first impact will as be psycological