Assume that activity P has the following times:

Early start time (ES) = 4 days

Early finish time (EF) = 11 days

Latest start time (LS) = 6 days

Latest finish time (LF) = 13 days

Which of the following statements is TRUE about activity P?

a. Activity P takes 2 days to complete

b. Activity P is on the critical path

c. Activity P has 2 days of slack time

d. Activity P is the first activity of the project

e. None of the above are true

Assume that activity P has the following times:

Early start time (ES) = 4 days

Early finish time (EF) = 11 days

Latest start time (LS) = 6 days

Latest finish time (LF) = 13 days

If disaster strikes and activity P will take 20 days to complete rather than the original activity duration (assume that it started at the ES time), by how long will the completion of the project be delayed?

a. 20 days

b. 13 days

c. 11 days

d. 7 days

Explanation / Answer

1.

(ES) = 4 days

(EF) = 11 days

(LS) = 6 days

(LF) = 13 days

Slack = LF - EF or LS - ES

   = 13 - 11 = 2

c. Activity P has 2 days of slack time

2.

Earlier Activity Duration = EF - ES = 11 - 4 = 7 days

If disaster strikes and activity P will take 20 days to complete rather than the original activity duration.

by (20 - 7) = 13 days will take for completion of the project be delayed.

b. 13 days