As part of a major plant renovation project, the industrial engineering departme
ID: 443828 • Letter: A
Question
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:
Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round your answers to 1 decimal place.)
Determine the minimum number of stations needed. (Round your answer to the next whole number.)
Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.
Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation. (Round your answer to 1 decimal place. Omit the "%" sign in your response.)
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:
Explanation / Answer
a. Precedence diagram
b.
The minimum cycle time =maximum cycle time=1.2 minutes
Maximum cycle time=.2+.4+.2+.4+1.2+1.2+1.0=4.6 minutes
CT= (480 minutes/day )/(240 units/day) = 2 minutes
c.
Maximum number of stations needed.
N= sum of task times/CT=4.6minutes/2minutes=2.3 rounded to 3
d. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.
e. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation.
% idle=(.8+.8+...+1.0)/(4stations*2minutes)=42.5%
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.