An order for 200 of a product is processed on work centers A and B. The setup ti

ID: 444097 • Letter: A

Question

An order for 200 of a product is processed on work centers A and B. The setup time on A is 30 minutes, and run time is 20 minutes per piece. The setup time on B is 50 minutes, and the run time is 10 minutes per piece. Wait time between the two operations is four hours. The move time between A and B is ten minutes. There is no waiting after operation B. The move time from B into stores is 15 minutes. There is no queue at either workstation. Calculate the total manufacturing lead time for the order. A. 4435 minutes

B. 5435 minutes

C. 6435 minutes

D. 7435 minutes

E. None of them

Explanation / Answer

As per the given data :

Total Manufacturing Lead Time :

Operation time is caluculated = Set up time + Run time * no. of products .

Therefore :

Operation time of A = 30 mins + 20 mins * 200 products = 4030.

Operation time of B = 50 mins + 10 mins * 200 products = 2050.

Total Manufacturing lead time is adding up all the mins = 6345 mins.

Option is E : none of them