The Laurenster Corporation has determined the client will pay them a 10,000 bonus if they complete the project in Problem 11-33 in 14 weeks or less. The associated normal times and costs as well as the crash times and costs are shown below.
Activity Normal Time Crash Time Normal Cost Crash Cost
A 3 2 600 1200
B 6 4 1200 2400
C 5 2 1200 2400
D 4 3 1200 1800
E 7 6 1200 1800
F 7 4 1200 3000
G 5 1 2400 4800
H 5 2 1200 3000
I 5 3 1800 2400
J 2 2 300 300
K 4 4 300 300
L 3 3 300 300
Considering the costs involved to crash the project, determine if the Laurenster Corporation should crash teh project to 14 weeks to receive the bonus
Explanation / Answer
yes, it can crash the project to get bonus with in the specifications only.