The total flow time for the sequence developed using the FCFS rule= ___ days (ro
ID: 448372 • Letter: T
Question
The total flow time for the sequence developed using the FCFS rule= ___ days (round to two decimal places.)
sequence is:
1 SY-11
2. RG-05
3. BR-02
4. DE-06
5. CX-01
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241 Date Job Due Duration Job BR 02 CX 01 DE -06 RG -05 SY-11 (days) 35 40 30 15 25 Received Date 230 235 231 228 225 320 360 310 300 270Explanation / Answer
taken begining date from 240 since 241 will be working initating day so will be inclusive of 25 days of work for first activity.
Job DJR Begin work Flow Time due day SY-11 225 240 25 265 270 RG-05 228 265 15 280 300 BR-02 230 280 35 315 320 DE-06 231 315 30 345 310 CX-01 235 345 40 385 360Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.