Bragg\'s Bakery is building a new automated bakery in downtown Sandusky. Here ar
ID: 449572 • Letter: B
Question
Bragg's Bakery is building a new automated bakery in downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed.
Bragg's loses $3,500 in profit per week for every week the bakery is not completed. How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3,500?
Bragg's Bakery is building a new automated bakery in downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed.
ACTIVITY PREDECESSOR NORMALTIME (WEEKS) CRASH
TIME (WEEKS) EXPEDITING
COST/WEEK A — 7 5 $ 3,200 B A 9 7 4,000 C A 5 3 3,700 D B, C 8 6 2,300 E C 4 3 2,600 F D, E 3 2 5,400 a. Identify the critical path. A-C-D-F A-C-E-F A-B-D-F b. What is the normal project length? Normal project length weeks c. What is the project length if all activities are crashed to their minimum? Project length weeks d.
Bragg's loses $3,500 in profit per week for every week the bakery is not completed. How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3,500?
The project will take weeksExplanation / Answer
a. critical path= A-B-D-F
b. normal project length= 27 weeks
c. after crash the time is = 20 weeks
d. 20 weeks only