Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESS

ID: 451238 • Letter: T

Question

TIMES (days)

Activity

Start Node

Finish Node

OPTIMISTIC

to

MOST LIKELY

tm

PESSIMISTIC

tp

A

1

2

25

34

61

B

1

3

21

27

39

C

2

5

18

42

66

D

3

4

32

50

68

E

4

5

8

20

44


Standard Deviation =


Activity C………te =


Standard Deviation =


Activity D………te =


Standard Deviation =


Activity E………te =


Standard Deviation = 6


Path 1 – 2 – 5
Mean Time =


Standard Deviation =10


Path 1 – 3 – 4 – 5
Mean Time =


Standard Deviation =

Save

TIMES (days)

Activity

Start Node

Finish Node

OPTIMISTIC

to

MOST LIKELY

tm

PESSIMISTIC

tp

A

1

2

25

34

61

B

1

3

21

27

39

C

2

5

18

42

66

D

3

4

32

50

68

E

4

5

8

20

44

Explanation / Answer

Accepted Activity Duration = {to + (4*tm) + tp}/6

Standard Deviation = (tp - to)/6