The S&OP team at Kansas Furniture, has received estimates of demand requirements
ID: 451774 • Letter: T
Question
The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming stockout costs for lost sales of $100 per unit, inventory carrying costs of $30 per unit per month, and zero beginning and ending inventory, evaluate the following plan on an incremental cost basis: Plan A: Produce at a steady rate ( equal to minimum requirements) of 1,200 units per month and subcontract additional units at a $70 per unit premium cost. Subcontracting capacity is limited to 500 units per month. ( enter all responses as whole numbers )
Month Demand Production Ending inventory Subcontract (Units)
1. July 1200 1,200 0 ?
2. August 1300 1,200 0 ?
3. Sept 1200 1,200 0 ?
4. Oct 1700 1,200 0 ?
5. Nov 1650 1,200 0 ?
6. Dec 1400 1,200 0 ?
Explanation / Answer
Subcontracting units = Demand - (Production + Ending inventory of previous month ), limited to 500 per month .
Month Demand Production Ending inventory Subcontract (Units) 0 July 1200 1200 0 0 August 1300 1200 0 100 Sept 1200 1200 0 0 Oct 1700 1200 0 500 Nov 1650 1200 0 450 Dec 1400 1200 0 200Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.