Seven jobs have arrived to work center ldquo X dquo to be processed. Determine the sequence to process the jobs by applying each of the following rules: FCFS (First Come First Served) SPT (Shortest Processing Time) EDD (Earliest Due Date) Critical ratio (CR) Moore's algorithm For each of the sequences above, compute the following metrics of performance: The number of jobs that won't meet the due date The average job lateness, in days late/job The average flow time per job Summarize your results in a table; specify which is the sequence that optimizes each of the performance criteria

Explanation / Answer

Let us first apply priority to jobs on the basis of First Come First Served

JOB

JOBS IN SYSTEM

JOB TIME AT WORK CENTER “X” (DAYS)

CUMULATIVE FLOW TIME

DUE DATE (DAYS FROM NOW)

DIFFERENCE IN DELIVERY SCHEDULE

A

7

3

3

15

-

B

6

7

10

30

-

C

5

6

16

18

-

D

4

5

21

20

1

E

3

2

23

22

1

F

2

9

32

21

11

G

1

4

36

25

11

TOTAL

36

141

24

Let us now apply priority to jobs on the basis of Shortest Processing Time

JOB

JOBS IN SYSTEM

JOB TIME AT WORK CENTER “X” (DAYS)

CUMULATIVE FLOW TIME

DUE DATE (DAYS FROM NOW)

DIFFERENCE IN DELIVERY SCHEDULE

E

7

2

2

22

-

A

6

3

5

15

-

G

5

4

9

25

-

D

4

5

14

20

-

C

3

6

20

18

2

B

2

7

27

30

-

F

1

9

36

21

15

TOTAL

36

113

17

Let us now priority to jobs on the basis of earliest due date

JOB

JOBS IN SYSTEM

JOB TIME AT WORK CENTER “X” (DAYS)

CUMULATIVE FLOW TIME

DUE DATE (DAYS FROM NOW)

DIFFERENCE IN DELIVERY SCHEDULE

A

7

3

3

15

-

C

6

6

9

18

-

D

5

5

14

20

-

F

4

9

23

21

2

E

3

2

25

22

3

G

2

4

29

25

4

B

1

7

36

30

6

TOTAL

36

139

15

Let us now priority to jobs on the basis of critical ratio

The Slack time for each job is calculated as follows

JOB

JOB TIME AT WORK CENTER “X” (DAYS)

DUE DATE (DAYS FROM NOW)

SLACK TIME (DAYS)

CRITICAL RATIO

A

3

15

12

5

B

7

30

23

4.3

C

6

18

12

3

D

5

20

15

4

E

2

22

20

11

F

9

21

12

2.3

G

4

25

21

6.25

JOB

JOBS IN SYSTEM

JOB TIME AT WORK CENTER “X” (DAYS)

CUMULATIVE FLOW TIME

DUE DATE (DAYS FROM NOW)

DIFFERENCE IN DELIVERY SCHEDULE

F

7

9

9

21

-

C

6

6

15

18

-

D

5

5

20

20

-

B

4

7

27

30

-

A

3

3

30

15

15

G

2

4

34

25

9

E

1

2

36

22

14

TOTAL

36

171

38

Let us now priority to jobs on the basis of Moore’s Algorithm

Let E denotes set of early jobs and L denotes set of late jobs

Initially all jobs are set in E and L is empty

Order all jobs in set E as per EDD rule

Let 0 means non-tardy job and 1 means tardy job

As per sequence in set E there are 4 tardy jobs and 1st tardy job is F

JOB

JOBS IN SYSTEM

JOB TIME AT WORK CENTER “X” (DAYS)

CUMULATIVE FLOW TIME

DUE DATE (DAYS FROM NOW)

DIFFERENCE IN DELIVERY SCHEDULE

TARDY/NON TARDY JOBS

A

7

3

3

15

-

0

C

6

6

9

18

-

0

D

5

5

14

20

-

0

F

4

9

23

21

2

1

E

3

2

25

22

3

1

G

2

4

29

25

4

1

B

1

7

36

30

6

1

TOTAL

36

139

15

SET E (A-C-D-E-G-B)

SET L (F)

JOB

JOBS IN SYSTEM

JOB TIME AT WORK CENTER “X” (DAYS)

CUMULATIVE FLOW TIME

DUE DATE (DAYS FROM NOW)

DIFFERENCE IN DELIVERY SCHEDULE

TARDY/NON TARDY JOBS

A

6

3

3

15

-

0

C

5

6

9

18

-

0

D

4

5

14

20

-

0

E

3

2

16

22

-

0

G

2

4

20

25

-

0

B

1

7

27

30

-

0

TOTAL

36

89

FINAL SEQUENCE (A-C-D-E-G-B-F)

JOB

JOBS IN SYSTEM

JOB TIME AT WORK CENTER “X” (DAYS)

CUMULATIVE FLOW TIME

DUE DATE (DAYS FROM NOW)

DIFFERENCE IN DELIVERY SCHEDULE

A

7

3

3

15

-

C

6

6

9

18

-

D

5

5

14

20

-

E

3

2

16

22

-

G

2

4

20

25

-

B

1

7

27

30

-

F

4

9

36

21

15

TOTAL

36

125

15

Final results are summarized as under

JOB

JOBS IN SYSTEM

JOB TIME AT WORK CENTER “X” (DAYS)

CUMULATIVE FLOW TIME

DUE DATE (DAYS FROM NOW)

DIFFERENCE IN DELIVERY SCHEDULE

A

7

3

3

15

-

B

6

7

10

30

-

C

5

6

16

18

-

D

4

5

21

20

1

E

3

2

23

22

1

F

2

9

32

21

11

G

1

4

36

25

11

TOTAL

36

141

24