Liberty University Portal X Bb 201620 Sp X M Chapt 12 ter operations Management x Ch online C ezto.mheducation.com /hm.tpx Problem 12-3 The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Amount Item Lead Time on Hand Direct Components End L(2), C(1), K (3) 10 B (2), J(3) 15 G(2), B (2 20 H(4), B(2) 30 30 a. don't units of the end item MRP to be assembled, how many additional units of B are needed? (Hint You plan.) are need to develop an f 42 Additional units b. An order for the end item is scheduled to be shipped at the start of week 8. What is the latest week that he order can be started and s be ready to ship on me? (Hint You don need to develop an MRP plan The latest week HE Search the web and Windows 7:58 PM 5/11/2016Explanation / Answer
A.
End item
Gross requirement = 42 units
On-hand invt. = 0
Net requirements = 42 units
Component B:
units required per end item = 2 units
Gross req. = 42*2 = 84 units
On-hand invt. = 30 units
Net Reqt. = 84 - 30 = 54 units
Additional units of Component B = 54 units
B.
Planned order receipt for end items = 8th week
Lead time for end item = 1 week
Planned order release for end items = 7th week
Planned order receipt for all components = 7th week
Maximum component lead time of componenets = 3 weeks
planned order relaease for components with LT of 3 weks = 7 - 3 = 4th week
Thus, latest week thaht the order can be started and still be ready to ship on time is 4th week.