Question 3.3. (TCO 1) The project objectives are defined by (Points : 5) A. the

ID: 457827 • Letter: Q

Question

Question 3.3. (TCO 1) The project objectives are defined by (Points : 5) A. the project team. the stakeholders and project manager. B. the project manager and project team. C. the management team. D.the project manager. Question 4.4. (TCO 2) At the end of the risk workshop, the two items identified are (Points : 5) A. the event that triggers the risk and the effect of the risk on the project. B. the event that triggers the risk and its probability of occurring. C. the identification of the risks and their impacts. D. the names of the risks and who is the risk owner. the risk triggers and responses.

Explanation / Answer

3.3. The correct answer is option D.

Project manager is responsible for defining and communicating the objectives to project team and stakeholders.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote